CONSTRUCTION MANAGEMENT STAGE DELIVERABLES

Stage 3: Design Development

STAGES

CLIENTS

BT

CONSULTANTS

CM-BT

STAGE 3 - DESIGN DEVELOPMENT

 

Definition  

Manage, co-ordinate and integrate the detail design development process within the project scope, time, cost and quality parameters.  

 

Standard Services  

  • Define and agree preliminary scope of construction works.

  • Prepare Preliminary Construction Programme.

  • Provide the necessary lead times required to prepare a detailed Design and Documentation Programme.

  • Review and recommend practical and cost effective construction alternatives to consultants’ designs.

  • Attend the appropriate planning, co-ordination and management meetings as required.

  • Review designs by consultants in relation to constructability requirements.

  • Review designs by consultants in relation to Health and Safety requirements during construction and provide input if required on related practical and cost issues.

  • Provide detailed cost information as required by the cost consultant for estimating, budgeting and cost reporting purposes.

  • Prepare and submit a proposed method statement for the construction of the works.

 

Deliverables

  • Preliminary scope of construction works.

  • Preliminary Construction Programme.

  • Schedule of agreed lead times for construction documentation.

  • Proposed Construction Method Statement.

  • Approval by Principal Agent of above.

Client approval to  proceed to Stage 4